- Dredge motors - Kenmare has completed the installation of new dredge motors, now designed and manufactured to appropriate specifications. This allows greater throughput of concentrate to the MSP.
- Vibrating screens - throughput at the MSP had been limited by the screens initially installed. These have now been replaced and are working to plan.
- Electricity - previously unstable power supply issues have been addressed by Kenmare and no longer have a material adverse impact on production.
- Zircon and rutile circuits - these are now producing minerals to specification and the contractor is working on achieving the agreed recovery rate.
- Roaster plant - the contractor has still to complete this facility. The roaster plant improves the quality of certain finished products. However, given strong market demand and the good quality of minerals produced to date, this has not been a commercial disadvantage.
Update on engineering matters previously notified to the market
| Source: Kenmare Resources
Recommended Reading
-
Kenmare Resources plc (“Kenmare” or the “Company” or the “Group”) 25 March 2026 2025 PRELIMINARY RESULTS Kenmare Resources plc (LSE:KMR, ISE:KMR), one of the leading global producers of titanium...
Read More -
This announcement contains inside information. Kenmare Resources plc(“Kenmare” or “the Company” or “the Group”) 9 March 2026 Update on Implementation Agreement Kenmare Resources plc (LSE:KMR,...
Read More